SUNSET HILL Construction Process.

I. Excavation:

From the stable ground we excavated and we fill in with big plinths below and smaller stones on top and we cover them with nylon, that way we prevent humidity. Then we mold 6-7cm concrete and above that we mold 45-50cm 'Betorantie' (thick-strong concrete with iron reinforcing), that way we accomplish strength to our iron shell. All this procedure makes our foundation more resistant to earthquakes and other exhaustions.

2. Brickwork:

The outside brickwork will be built of 25cm thick bricks with special heat and sound insulation. 9cm bricks will used for the interior walls. When all the walls are built to a height of 2,20m height we mold the corner columns for a better connection and above all this we mold the 'senaz or ring' (15cm thick concrete with iron reinforcing). At the height of 2,80m we mold a second 'senaz or ring' of 20cm height with irons where timber beams of the roof will rest.

3. Roof work:

. The roof will be built as below:
. Main beams of 15 x15cm thickness.
. Wood boards of 2cm.thickness and 20cm.width. . Insulation of 3cm.thickness.
. Pitch paper.
. Concrete tiles in cream color.
. Gutters at the roof edge.

The interior of the roof will have exposed beams.

4. Exterior Coating:

As a first layer we use insulating waterproof solution 'revinex'. As a second hand we use a covering of clay and cement 3cm thick. As a last layer we use a covering of marble and lime 1/2cm thick.

5. Interior Coloring:

We proceed as below:

. Rubbing to smooth the surface.
. Primer with acrylic application.
. Fill wherever is necessary.
. Application with bionomic double layer plastic color.

Doors

. Application with insulating polyester.
. Application with "SOUPFARER".
. Application of a two-component veneer.

Ceilings

. Application with "PRIMER".
. Application with a two-layer water-soluble lacquer.

6. Electrical:

In each bedroom there will be a light on the ceiling, three wall plugs, one phone-point, two on-off switches for the light in the room and one for the balcony. In each bathroom there will be a light at the wall-mirror, a light on the ceiling, one on off switch and two wall plugs. In the living room there will be a light on the ceiling, four wall plugs, one on-off switch for the balcony light and others for the living room lights and a phone-plug. In the dining room there will be one light on the ceiling, on-off switch and three wall plugs. The kitchen will have one ceiling light and an and off switch, lights under the upper cabinets with an on-off switch, on and off switches for the balcony light and four wall plugs. The hallway will have enough on and off switches for the lights in the living room, the dinning room, the hallway and the

outdoor lights at the main entrance. All the balconies will have one or two wall plugs. The garage will have in the interior two lights on the ceiling and four wall plugs and on the outside wall there will be two wall plugs and enough on and off switches for the lights. All the on-off switches and the wall plugs will be 'Legrand', or any other manufacturer of similar quality, in white colour and the electricity will be three phase.

7. Plumbing:

Each room will have one heat radiator big enough to provide the heat that each demands per cubic meters. The heat system consists of one boiler burner and a 500-liter plastic cistern for fuel. There will be hot water even when the heat radiators are closed. The equipment will be housed behind the garage.

       Bathrooms:

The small WC. will have one basin with a wall mirror, one toilet and one shower cabin. The big bathroom will have one basin with a wall mirror, one toilet and one bathtub. Both will be fully provided with taps, soup-dishes and towel racks. All the plumbing fixtures will be Ideal Standard.

     Kitchen:

There will be plumbing for the washing machine and the dishwasher.
There will be three water taps outside the house. The whole piping installation will be made with plastic piping.

8. Kitchen Equipment:

Kitchen cabinets will be M DF interior, wood doors and countertop granite.

9. Tiles:

. Interior flooring - 18 € psm
. Bathrooms - 20 psm
. Balconies - 15 € psm
. Garage - 15 € psm
. Kitchen wall tiles - 20 psm

10. Interior doors:

All the doors in the kitchen and the bathrooms will be made from PVC.

11. Exterior doors:

        . Aluminum main entrance.
        . P. V. C. double glaze windows and French windows with screens and aluminum sun blinds.
      . Aluminum and glass kitchen door.

12. Closets:

All the interior of the bedroom closets will be made by M DF and the closet doors made from wood.

13. Satellites:

This can be installed on request and at an additional cost.

14. Exterior Environment:

The gate columns at the outside main entrance and the road from the entrance to the house garage will be made with concrete. The concrete road of 1,20m width will connect to the garage. Also another concrete path of 0,80m width will surround the house.

15. Drainage System:

There will be built a 36 cubage draining system (septic tank) for the three houses to use, that means each house will have 12 cubic meters, which is the standard.

16. Communal Road:

Big stones below and smaller stones on top will make the communal road. At the edges of the road there will be built a channel for drainage.

17. Electricitv and Telephone:

The electricity of each house will be three phase. There will be one main telephone box for the three houses.